Restoration on Comana wetlands, Romania > Barrier #1818

Barrier type
Other
Barrier role
main barrier
Comments
Barriers for the implementation of the measures were due to the process of public procurement for contracts regarding the supply / works / services, which consisted in appeals and had as a consequence procedures which led to delays in the project implementation. Addendum were necessary in order to extend the implementation period. This resulted from the inflexibility to redistribute savings and so required using beneficiaries own funds.